  #1  
Old 20th March 2003, 12:53
Andreas's Avatar
Andreas Andreas is offline
Senior Member
 
Join Date: Nov 2001
Location: Hannover
Posts: 263
Andreas is on a distinguished road
Baan: ERP LN FP5 - DB: Oracle 10g - OS: AIX, SLES
Question Routing unit and fixed duration time

Hi,
i have the folowing problem:
I'm on Vc.
We have a routing with a routing unit that is different from 1 (suppose 100).
In this routing we have some tasks with fixed duration time (suppose 100 min).
When we plan a production order via cp or even manually maintain a production order
for an item with this routing, then the production time for this routing is given
as fixed duration time divided by routing unit in production planning.
In our case the time is 100 min / 100 = 1 min.
In my opinion this is wrong (PEG says this is standard functionallity).
Fixed duration time is fixed duration time! no matter if routing unit or lot size
is 1, 2, 3 or 10000.
Now my question to people who are on Baan IV:

Is the funtionality the same or is it different?
Reply With Quote
Sponsored Links
  #2  
Old 25th March 2003, 03:02
Paul P's Avatar
Paul P Paul P is offline
Guru
 
Join Date: Jul 2002
Location: Jakarta, Indonesia
Posts: 797
Paul P is on a distinguished road
Baan: BaanIV, BaanERP - DB: SQL Server, Informix, Oracle - OS: Windows, HP-UX
Dear Andreas,

BaanIV doesn't support fixed duration production operation by default. You need a work around in BaanIV to model that

Rgds,
Paul
Reply With Quote
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
how many parcels are there on one pallet? volkan Manufacturing & Supply Chain 5 4th June 2002 11:47


All times are GMT +2. The time now is 15:35.


©2001-2017 - Baanboard.com - Baanforums.com