  #1  
Old 19th December 2007, 16:19
metropoj metropoj is offline
Senior Member
 
Join Date: Feb 2004
Location: Oshawa
Posts: 223
metropoj is on a distinguished road
Baan: LN FP7 - DB: MSSQL - OS: Win 7
Question Maintain Gen Routing Setup Time Question
Baan: Other/Unknown

We set up our Generic Routing by the unit ordered.

At some point, it was decided that for some "Operations" under Maintain Generic Routing, the "Setup" field would be used to represent the setup of ONE unit. It appears as though the company would like to account for this setup time PER UNIT ordered.
For example, 1 Rail operation had a setup time of 30 minutes. IF the customer Ordered 2 rails, they want to account for 60 min setup time, 30 min per rail unit.

I know that 'run_time' or 'quantity' allows me in the constraints to access the 'Run Time' or 'Quantity' field from the operations.

Is anyone familiar if I can use the variable 'setup' in constraint program to read that value from the 'Setup' routing operations ?

I hope that was clear ?
Reply With Quote
  #2  
Old 20th December 2007, 06:15
David Eagar David Eagar is offline
Senior Member
 
Join Date: Jun 2004
Location: Far South Coast, NSW, Australia
Posts: 106
David Eagar is on a distinguished road
Baan: 5c (SP16) - DB: SQL2005 - OS: Windows 2003
To get to basics in your process - are you sure that it takes twice as long to set up your machinery to make 2 items instead of one?
Without a mod, I think you will need to set up quantity dependant routings to achieve your goal
Reply With Quote
  #3  
Old 20th December 2007, 15:05
metropoj metropoj is offline
Senior Member
 
Join Date: Feb 2004
Location: Oshawa
Posts: 223
metropoj is on a distinguished road
Baan: LN FP7 - DB: MSSQL - OS: Win 7
In some of these constraints, they were used to specify the set up time to prep 'per unit made' as there were certain operations that did require exactly the same amount of time per unit.

In this instance, we do in fact need the setup time per unit made. We cannot use the run-time because our product is also length based and regardless of length we still require the same set up time per unit ....

We are finding in review that the configuration only captures the initial setup time. I want to be able to capture the number of units ordered and multiply by the set up time to capture the costs more correctly ...
Reply With Quote
Sponsored Links
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Using Routing vs Using Lead Time curiosis Manufacturing & Supply Chain 10 13th March 2014 17:27
AFS: Maintain Production Order: Routing field problem khadarBaaNBoard AFS/DDC/OLE: Function servers 1 30th March 2006 18:09
Avg setup time in routing operation namasamaran Manufacturing & Supply Chain 2 30th September 2004 17:39
Routing unit and fixed duration time Andreas Manufacturing & Supply Chain 1 25th March 2003 03:02