  #1  
Old 16th December 2003, 16:57
jpadilla jpadilla is offline
Senior Member
 
Join Date: Jun 2002
Location: Mexico
Posts: 163
jpadilla is on a distinguished road
Baan: IVc4 - DB: Informix - OS: AIX
adding service order to a project

Hi,

We are using, estimated costs on small project module, we have the following scenario:

Actually when a project is invoiced, we just add a line in sales order for a cost item "SERVICE", what I want to do is to start the service order use, creating a service order for the installation linking it to a project.

What do I need to do if I want that all the service order cost (Material, expenses,other) go directly to project cost.??

I 'm using Estimated Cost, I think that service costs goes as general costs of the project and it is only important for Actual Cost

Am I right??

any suggestion??

Regards
JP
Reply With Quote
  #2  
Old 15th January 2004, 12:11
Jeff Ball's Avatar
Jeff Ball Jeff Ball is offline
Senior Member
 
Join Date: Aug 2001
Location: Rainy end of UK
Posts: 115
Jeff Ball is on a distinguished road
When you set up the Installation, there is a field for Project, which links the Installation to a (PCS) project. When you book costs to a service order performed on that installation, the project reference will be picked up. This is tru for both estimated and actual costs, as they are in the same table with a status flag to show which they are.
Reply With Quote
Sponsored Links
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Deleting Lines In Servicxe Order after making PO riazsayeed Project & Services 2 6th July 2004 06:14
Work order on subcontractor mukeshl11 Finance, Invoicing and Integration 1 5th August 2003 22:23
problem while generating service order form service order quotation ajjugarg2 Project & Services 0 31st July 2003 13:10
Adding a line to a Sales Order. wricks Tools Development 8 7th February 2003 03:44
Generate Project Structure from sls order sturla Manufacturing & Supply Chain 1 5th December 2001 12:16


All times are GMT +2. The time now is 21:15.


©2001-2017 - Baanboard.com - Baanforums.com