  #1  
Old 7th October 2003, 14:55
newtobaan's Avatar
newtobaan newtobaan is offline
Member
 
Join Date: May 2003
Posts: 36
newtobaan is on a distinguished road
Baan: BaanC4 SP19 - DB: Oracle 9i - OS: HP UX
item selection in Generate MRP session

Hi,

Quick question on generate MRP. While running this session we can select the item we want to run MRP for. How does this item selection work? Can we select a top level part number (which is an MPS item) and will the MRP sesssion then generate MRP for all the components below it (if the components are MRP items).
What if I select a component (which is an MRP item), will it generate MRP for the rest of the components (which are MRP) in the BOM.

Thanks

Bhaswar
Reply With Quote
  #2  
Old 7th October 2003, 15:36
dmcgrath's Avatar
dmcgrath dmcgrath is offline
Member
 
Join Date: Sep 2001
Location: Nottingham, England
Posts: 41
dmcgrath is on a distinguished road
Baan: Baan IVc3 Sch0 & IVc4 AGS0 - DB: Informix 7.31 UC6 & Informix 9.4 - OS: Solaris 2.6 & Solaris 9
"While running this session we can select the item we want to run MRP for. How does this item selection work? Can we select a top level part number (which is an MPS item) and will the MRP sesssion then generate MRP for all the components below it (if the components are MRP items)"

MRP can not be run against the top level item that is an MPS item.


"What if I select a component (which is an MRP item), will it generate MRP for the rest of the components (which are MRP) in the BOM"

If the MRP item is a purchased item, MRP will only be generated for this item. If the MRP item is a manufactured item , MRP will be generated for this item and all subcomponents in the BOM of this item.
Reply With Quote
Sponsored Links
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
line item not found in dem session savitr Tools Development 1 7th February 2004 23:44