  #1  
Old 26th March 2003, 01:27
rosalbaperez rosalbaperez is offline
Member
 
Join Date: Oct 2001
Location: San Diego
Posts: 32
rosalbaperez is on a distinguished road
Baan: IVc4, SP4 - DB: MS SQL 2000 - OS: WIN 2K
Operation Complete Date

The "Report Operations Completed" session does not have a field to capture the date when the operation was completed. Is this a functionality issue or it is captured somewhere else? like in Hours Accounting module?

How are you dealing with this?

Thanks
Rosalba
__________________
Rosalba Perez
Reply With Quote
  #2  
Old 27th March 2003, 04:13
shah_bs's Avatar
shah_bs shah_bs is offline
Guru
 
Join Date: Jan 2002
Location: Lewisville, Texas
Posts: 387
shah_bs is on a distinguished road
Baan: BAAN IVc3 with A&D2.2b - DB: ORACLE 9 - OS: HPUX
You will need to customize to achieve your requirement. A field can be added to the Production Planning table (tisfc010) and one library need to be modified so that whenever the operation is marked as completed, this field is accordingly updated.

Alternatively, the new field can be added to the form of Report OPerations Complete and the date defaulted to 'today'. This would not need any source code changes.
Reply With Quote
  #3  
Old 2nd April 2003, 13:12
Paul P's Avatar
Paul P Paul P is offline
Guru
 
Join Date: Jul 2002
Location: Jakarta, Indonesia
Posts: 797
Paul P is on a distinguished road
Baan: BaanIV, BaanERP - DB: SQL Server, Informix, Oracle - OS: Windows, HP-UX
Dear Rosalba,

It might not be as straight forward, but whenever certain quantity is reported as produced against a production order, an entry will be created in the Financial Integration record with origin of Production and transaction type Completion. The date you're looking for is recorded there

Rgds,
Paul
Reply With Quote
  #4  
Old 15th April 2003, 04:55
rosalbaperez rosalbaperez is offline
Member
 
Join Date: Oct 2001
Location: San Diego
Posts: 32
rosalbaperez is on a distinguished road
Baan: IVc4, SP4 - DB: MS SQL 2000 - OS: WIN 2K
Thanks

Hi everyone and thanks for your replies. I think adding the completion date to the table will be the best option.

Paul P: I think the date that is recorded in the integration transaction is when the production order is complete and not the each operation.

Thanks!
Rosalba
__________________
Rosalba Perez
Reply With Quote
Sponsored Links
  #5  
Old 15th April 2003, 14:48
Paul P's Avatar
Paul P Paul P is offline
Guru
 
Join Date: Jul 2002
Location: Jakarta, Indonesia
Posts: 797
Paul P is on a distinguished road
Baan: BaanIV, BaanERP - DB: SQL Server, Informix, Oracle - OS: Windows, HP-UX
Dear Rosalba,

BaanERP does record the completion of each operation in the financial integration record. Sorry, it might not be the case with your BaanIV

Rgds,
Paul
Reply With Quote
  #6  
Old 16th April 2003, 03:15
rosalbaperez rosalbaperez is offline
Member
 
Join Date: Oct 2001
Location: San Diego
Posts: 32
rosalbaperez is on a distinguished road
Baan: IVc4, SP4 - DB: MS SQL 2000 - OS: WIN 2K
Thanks

Thanks for your help!

Rosalba
__________________
Rosalba Perez
Reply With Quote
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Time stamp and user who report an operation complete khyou99 Manufacturing & Supply Chain 5 12th August 2004 14:09
Is backup complete ??? learner Operating Systems & Databases 3 15th January 2003 07:05
How to capture date and quantity reported complete by operation Bryan Manufacturing & Supply Chain 15 17th November 2002 19:52


All times are GMT +2. The time now is 23:04.


©2001-2017 - Baanboard.com - Baanforums.com