Baanboard.com

Go Back   Baanboard.com > Forum > Baan Quick Support: Functional & Technical > Distribution, Transportation & Warehousing

User login

Frontpage Sponsor

Main

Google search


Poll
For ERP LN feature pack upgrade, what method of install are you using?
Installation Wizard into existing VRC
36%
Installation Wizard into new VRC
36%
Manual into existing VRC
7%
Manual into new VRC
22%
Total votes: 45

Baanboard at LinkedIn


Reference Content

Reply
 
Thread Tools Display Modes
  #1  
Old 19th September 2017, 23:10
igor.hanzelic igor.hanzelic is offline
Newbie
 
Join Date: Feb 2012
Posts: 2
igor.hanzelic is on a distinguished road
Baan: LN 6.1 - DB: ORACLE - OS: unix
Purchase schedules - original date
Baan: ERP LN 6.1 FP10 (Infor ERP 10.4)

Hi,

We are looking for a partner with experience in optimizing processes in Infor LN. At the moment, we need advice primarily in the areas of planning, sales and purchasing. In the material procurement we use purchase schedules and we encountered the problem of managing changes in purchasing terms on purchase schedules.

Steps:
1. We send the purchase release to the supplier.
2. We receive the confirmed term from the supplier and on the basis of this we change the existing planned delivery date on the line of the purchase schedules. In this way, we provide realistic planning dates.
3. On the next version of the purchase release, the supplier no longer sees the original date because we changed it on the basis of the supplier's confirmation.

We would like the supplier to see the new version of the purchase release, despite the change of the original date! We send weekly delivery plan via EDI. To the suppliers that do not have EDI, we send delivery plan via e-mail. We want to find the right solution, can you help us with this?

We use the information system INFOR LN 10.4.
Reply With Quote
Sponsored Links
  #2  
Old 20th September 2017, 07:35
sasikanth's Avatar
sasikanth sasikanth is offline
Senior Member
 
Join Date: Jul 2009
Location: Hyderabad, Andhra Pradesh, India
Posts: 150
sasikanth is on a distinguished road
Baan: L.N 6.1 FP7, 10.3, 10.4 & 10.5 - DB: SQL Server - OS: Windows
Hello Hanzelic,

I strongly believe that, it needs a deep study on your current processes, both Business & Product, in order to optimize the processes.

I've worked on these concepts extensively, and should be able to help you - provided that you share the detailed information.

Please get connected on Skype "sasikanth.gil" (without Quotes), to discuss more and see how we can move ahead.
__________________
Sasi Kanth V
Infor ERP LN Solution Architect

Reach Me Out on LinkedIn | Never Miss an Update from LN Campus YouTube Channel
Reply With Quote
  #3  
Old 11th July 2018, 11:13
chandrajeet's Avatar
chandrajeet chandrajeet is offline
Junior Member
 
Join Date: Mar 2011
Location: Hyderabad
Posts: 7
chandrajeet is on a distinguished road
Baan: Infor LN FP2, FP7, FP9,FP 10.4,10.5 - DB: Oracle - OS: windows
Hi Hanzelic,

Before answering your question I would like to give you high level of overview how system generate purchase schedule.
The generated purchase schedule (supply) and lines are based on the delivery moments. EP groups all the orders to the nearest delivery moment before the supply with in the Horizon Date. In case no delivery moment before supply date it groups the supply to the immediate delivery moment after the supply.
Now how system would decide the firm requirement or planned requirement for example Current date to till 30 days it would be firm as we define in segment XX with length of 30 days plus system consider the Delivery moments & for planned After 30 days to till 10 weeks it would be Planned as if we define segment length for
segment “XXX” as 10 weeks plus system would consider nearest Delivery moments.

Now so far your question is concern If EDI is implemented than "MRL001" would be sent to your supplier once you print "print purchase release" as per your planed demand by considering segment length and delivery moments and again if there is any change in demand than system regenerate requirement type planed and firm by considering segment length and delivery moments.
We can use the session "Purchase Release line-Details by schedule" to track the Purchase schedule against release type (shipping schedule/Material release) and Release revision.
If any further clarification require or some requirement I misunderstood than please do send me the mail on chandrajeetkishore@gmail.com.
__________________
Thanks,
Chandrajeet Kishore

Last edited by chandrajeet : 11th July 2018 at 12:12.
Reply With Quote
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Default Receipt date for EDI Purchase Orders Jason Patte Distribution, Transportation & Warehousing 0 7th April 2010 16:08
Purchase Schedules - Material Release Date tbatchler Manufacturing & Supply Chain 0 24th September 2009 22:31
Purchase order date in order lines sathasivan Distribution, Transportation & Warehousing 3 19th May 2005 05:10


All times are GMT +2. The time now is 12:59.


©2001-2018 - Baanboard.com - Baanforums.com