View Single Post
  #1  
Old 28th April 2017, 00:13
conwedjpc conwedjpc is offline
Junior Member
 
Join Date: Apr 2017
Posts: 3
conwedjpc is on a distinguished road
Baan: 4c4 erpln 10.2.1 - DB: mssql - OS: unix x86
missing scheduled reciepts in MPS aggregated periods
Baan: Baan IVc4

We have been running a multilevel plan for several years.
using aggregation for multilevel links.
in the last 3 months the scheduled demand on the plan levels above (or below depending on your terminology) lost the scheduled reciepts numbers that have been there for a long time.
the actual planned customer orders and scheduled reciepts remain correct on the actual planned items level.
Does anyone know what I can do to reload those prior period actuals?
I have tried every combination I can think of to reload goods flow numbers although I figure that only happens at the bottom actual production level, and I have tried aggregating back up, but I am not even sure aggregation will impact the scheduled reciepts lines. I am unclear what choices kick off updating goods flow updates in MPS anyway. Seems a bit clearer on ERPLN than on Baan IV.
Reply With Quote