View Single Post
  #1  
Old 1st March 2017, 16:24
lotius81 lotius81 is offline
Junior Member
 
Join Date: Nov 2016
Posts: 25
lotius81 is on a distinguished road
Baan: Infor LN 10.4 - DB: SQL Server - OS: Windows Server 2008
Shifting orders by machine
Baan: Other/Unknown

One of the big problems we run into is properly scheduling orders. In one particular area all of the routing runs through a generic test stand machine set up in the system. There are currently a couple hundred orders scheduled to run that use this generic machine routing. In other areas we have separate machines (blow molding machines) that we sometimes need to reschedule as well. Let's say if someone calls in and I need to shut down a machine for 8 hours. But I also need to shift all of the orders that were scheduled to run against these machines forward 8 hours.

My question is is there a quick and easy way to reschedule production orders by machine and move them all forward or backward a specific number of hours? Or do orders have to be rescheduled individually, which for us is horribly inefficient.

Using Infor LN 10.4
Reply With Quote