rwm100 24th April 2017 16:13

Baan BOM Effectivity Dates
 
Can anyone advise where the maximum (date) is found for entering into the BOM Effectivity Date. We added one of 2040 and the Planning Engine fails to move past it. So the date is probably not recognised. Where is that limitation set? Can anyone help please?
Thanks
Should have said this is on Baan 5c.

mark_h 24th April 2017 16:37

Check your company calendar and make sure it goes out that far. That was the first thing that popped into my mind.

bdittmar 24th April 2017 17:40

15th Jan. 2038 should work
 
Quote:

Originally Posted by rwm100 (Post 202881)
Can anyone advise where the maximum (date) is found for entering into the BOM Effectivity Date. We added one of 2040 and the Planning Engine fails to move past it. So the date is probably not recognised. Where is that limitation set? Can anyone help please?
Thanks
Should have said this is on Baan 5c.

Hello,

15th of January 2038 should work in LN (5c also?).

40 years in the future !

Regards

rwm100 26th April 2017 23:03

Thanks - Resolved
 
Apparently its a System constraint any date after Jan 2038 is not recognised. Used to be 2030 in 5c originally but was changed at some stage through one of the service packs. Thanks for all your responses.